Gas Permit Process
Only a state licensed Plumber, Mechanical contractor or Residential Home Builder can pull gas permits.
Contractor will need the following
-
- Gas Application ID# and/or address
- Photo ID
- State contractors card
- Signed Contract indicating scope of work , materials and labor
- Letter of Authorization letter to pull permits if you are not the Contractor listed on Contractors Card or Owner of property.
- Master permit if applicable
- How many outlets/ Safety
If State Contractor license is expired no permits can be issued. If local contractor’s card has expired a fee of $40.00 will be added to the permit and a new card will be given.
Gas Permits
Application Filing Fee | $30.00 (Non-refundable) |
One to Four Outlets | $10.00 |
Each Additional Outlet | $2.00 |
One Unit (burner, furnace) | $5.00 |
Each Additional | $1.00 |
Inspections
For inspections contact appropriate inspectors located on Building Department Staff Directory.
-
- Monday – Friday 8:00 am -9:00 am for the same day inspections
- Monday – Thursday 3:30 pm – 4:30 pm for the next day inspections
Types of Inspections
-
- Rough- Pressure test 10-16
- Final
Posting of Permit
Work requiring a permit shall not commence until the permit holder or his agents posts the permit card inside a permit box in a conspicuous place on the premise. The permit shall be protected from weather and located in such position as to permit the Building Official or representative to conveniently make the required entries thereon. No work can be done until a permit is issued. The permit cards shall be maintained in position by permit holder until the certificate of Occupancy or Completion is issued by the Building Official. Inspection(s) will not be done by an inspector if the job site is missing permit drawings and a permit box.
The following are required inspections: If an inspection is not called for whether rough, final, etc. you are subject to lose City or State license. This includes all new construction, renovations and roof work (must provide a ladder).
The permit holder must call in his/her own inspections unless an authorization letter has been sent prior to the Building Department from the sub-contractors/ owner giving general contractor the okay to call in their work.