HomeConstruction and DevelopmentCertificate of Occupancy

Certificate of Occupancy

Residential

Documents required for Residential Certificate of Occupancy / Certificate of Completion

Certificate of Completion

  • Sub-Contractors list (you can find this list to fill out your subs, in the portal under the sub-contractor’s tab)
  • Final Building/Zoning inspections
  • All reinspection fees have been paid

Certificate of Occupancy (New Construction and projects that have more than 50% of work being performed)

  • Sub-Contractors list (you can find this list to fill out your subs, in the portal under the sub-contractor’s tab)
  • Elevation Certificate (this is needed if property is in the flood zone)
  • Truss Drawings (if you have trusses or building trusses)
  • Residential Compliance Form
  • Blower Door and Duct Blaster Testing
  • Termites Protection from the company
  • Sewer district inspection approval (if required please call 843-764-3072 to schedule)
  • Final Building/Zoning inspections
  • All reinspection fees have been paid

Everything listed above that is required must be attached and labeled pertaining to what you have attached in attachment. Certificate of Completion and Certificate of Occupancy are not issued on Friday.

Commercial 

Documents required for Commercial Certificate of Occupancy / Certificate of Completion

Certificate of Completion

  • Sub-Contractors list (you can find this list to fill out your subs, in the portal under the sub-contractor’s tab)
  • Elevation Certificate (this is needed if property is in the flood zone)
  • Sewer district inspection approval (if required please call 843-764-3072 to schedule)
  • Final Building/Zoning/Fire/sign inspections
  • Post Energy Compliance Com Check Mechanical (signed by Contractor/engineer)
  • Special inspections Report (if required)
  • Special Inspections Final statement (if required)
  • All reinspection fees have been paid

Certificate of Occupancy (New Construction and projects that have more than 50% of work being performed)

  • Sub-Contractor list (you can find this list to fill out your subs, in the portal under sub-contractor tab)
  • Commercial Compliance Form
  • Post Energy Compliance Com Check Mechanical (signed by Contractor/engineer)
  • Elevation Certificate (this is needed if property is in the flood zone)
  • Final MS4 (closeout letter) from public works department 843-460-1553
  • Sewer district inspection approval (if required please call 843-764-3072 to schedule)
  • Final Building/Zoning/Fire/sign inspections
  • Special inspections Report (if required)
  • Special Inspections Final statement (if required)
  • All reinspection fees have been paid

Everything listed above that is required must be attached and labeled pertaining to what you have attached in attachment. Certificate of Completion and Certificate of Occupancy are not issued on Friday.